Freedom of information response
Council Housebuilding
Under the Freedom of Information Act, I would like to request the following information.
These questions relate to new homes built by the council.
* 1) In the 2023/24 financial year (1 April 2023 to 31 March 2024) how many new homes of any tenure did the council complete?
* 1) a) Please can you provide a breakdown of those new build completions, by tenure (for example, how many were social rent, affordable rent, shared ownership, market sale, temporary accommodation, etc).
* 2) If the council has a council-owned housing company, in the 2023/24 financial year (1 April 2023 to 31 March 2024) how many new homes of any tenure did the company complete?
* 2) a) Please can you provide a breakdown of those completions, by tenure (for example, how many were social rent, shared ownership, market sale, temporary accommodation, etc).
* 3) How many homes does the council expect to build in the next five years (ie, from April 2024-March 2029)
* 4) If the council has a council-owned housing company, how many homes does it expect to build in the next five years (April 2024-March 2029)
Under the Freedom of Information Act, I would like to request the following information.
These questions relate to new homes built by the council.
* 1) In the 2023/24 financial year (1 April 2023 to 31 March 2024) how many new homes of any tenure did the council complete? 4 new build properties were completed
* 1) a) Please can you provide a breakdown of those new build completions, by tenure (for example, how many were social rent, affordable rent, shared ownership, market sale, temporary accommodation, etc). All 4 properties were affordable rent
* 2) If the council has a council-owned housing company, in the 2023/24 financial year (1 April 2023 to 31 March 2024) how many new homes of any tenure did the company complete? None
* 2) a) Please can you provide a breakdown of those completions, by tenure (for example, how many were social rent, shared ownership, market sale, temporary accommodation, etc). n/a
* 3) How many homes does the council expect to build in the next five years (ie, from April 2024-March 2029) 360
* 4) If the council has a council-owned housing company, how many homes does it expect to build in the next five years (April 2024-March 2029) n/a